The Electronmash company continues to participate in the reconstruction of the 110 kV Blagoveshchensk substation

29 June 2018

All news

The reconstruction of the substation carried out by Bashkirenergo LLC is carried out in several stages and is aimed at improving the quality and reliability of power supply to consumers in the residential and communal sectors of Blagoveshchensk, the surrounding villages of Ryazanovka, Nikolaevka, Andreevka, Suneyevka and Kurech, as well as industrial consumers.: Vostochnaya Rebar Company and Polyef JSC, which is a city-forming enterprise and the largest producer of terephthalic acid and polyethylene terephthalate in Russia.

 

Starting in July 2017, Bashkirenergo LLC's power engineers replaced the DC shield in the substation's general control center, chargers, batteries, and the shield for the substation's own needs. The first section of 6 kV tires has already been equipped with modern Eltema MVS manufactured by JSC Electronmash, and those delivered to the Eltima MVS facility in the 2nd quarter of 2018 are intended for the reconstruction of the second section of tires.


Manufactured and supplied to the 110/35/6 kV Blagoveshchensk substation, the 6kV Eltima switchgear takes into account the individual requirements of the Customer, has a high degree of protection from external influences, and is also designed for a high rated busbar current (4000A). The design of the control cabinets takes into account all modern requirements for reliable power supply and safe maintenance.

All news

Related materials

7 July 2021 Product
ELTEMA MV Switchgear 6 (10) kV
11 May 2011 Publication
New capacities - New opportunities